This following information relates to the tasks on a project Activity Predecessor Number o?

This following information relates to the tasks on a project Activity Predecessor Number of Days A -- 10 B -- 15 C A 5 D B 12 E C, D 14 F B 8 G D, F 15 H E 10 I E, G 6 J F, I 9 Answer the following questions: A. Determine the Early Start, Late Start, Early Finish, and Late Finish for each activity. B. What are the critical activities? C. How many days will the project take?